Club Development‎ > ‎Development‎ > ‎

Development Progress

The work on the new dressing rooms started last week and you can keep up-to-date on the progress by viewing thumbnails of photos here and you can view a slideshow of the photos here on the website. Foundations and all ground works gone in including footpaths and the site looks great. Thanks to Joe Grogan and his lads for all their hard work. The block layers started on the 13th October and will be on site up until Janurary.

25th November..Great work again this week...upstairs taking shape and below is how you get into the loft via the office...up via a pull down stairs.



9th Nov. Here is the lads who have been working on the new club house for the last 5 weeks. The club would like to thank each of them for their hard work...aren't they a hardy bunch!!!


2nd November. The office and 4 toilets are blocked out upstairs and they should be finished in the next few weeks with plastering etc...great work being down by all the lads on the Community Employment Scheme...thanks to them all for their hard work.

19th October. Lads working hard down in the field. The work has started on the upstairs and also tiling etc down in the kitchen.

11th September...we didn't do alot during the summer on the development side of things as football needed to be played...we did however at the start of September finish off the meeting room / kitchen. Here is a few photos of what it looks like. Thanks to Ray Bell and John Daly for doing the painting, Des Daly, Anthony Egan and Ger Rafferty for doing the plumbing and to everyone who supplied the materials for the job. The kitchen looks great in the new room...


End of August: Photo of the meeting room / Kitchen

31st May...Scaffolding taken down by Joe Grogan and his lads and the front tidied up and looking good...Thanks Joe for all your work on the project..you were a great help to the club..below is the new dressing rooms....the brackets were done by Tolman Camon and the finishing off was done by Martin Hanamy, Martin Grogan & Paddy Kenny. Saran also cleaned all the windows and doors(a very tedious job) and he has them spotless.. this is the great man in action...now everyone looking for to the charity game on Sunday...everyone welcome..BBQ, Music and refreshments will be there on the day..thanks to everyone who helped in getting the building ready for the charity game. We'll have our official opening later in the summer..we still have a few weeks work left..

19th May..What a busy few weeks..Tony, Mark, Kieran & Saran have all the dressing rooms plastered and will have outside fully finished by tomorrow. Aidan is paining away and we went with white for the main part of the building and grey around the bands and window sills.  Aidan added in some green around the windows..thanks to Paula Mulvey for help with colours. PJ and Eddie are painting the brackets for the new benches in the dressing rooms and Ciaran Grogan and Paddy Kenny are keeping everything moving. Eunan Healy is busy with the electrics and Des is busy with the plumbing as Ger is gone AWOL..The tilers also started today and are putting up tiles like there is no tomorrow...everything looking good for having the new facility open for the charity game we are hosting on the June bank holiday weekend..


26th April...The front is looking good...windows and doors all in..also the lads who are doing all the plastering..Tony, Mark, Kieran & Saran..

13th April - Upstairs to drying out....

Photo 7th April : What a week...part 2....Some of the windows and doors in....and it's only Thursday

Photo 6th April : What a week...Roof finished and windows and doors going in tomorrow and Friday.

Photo 28th March : Gerry and the lads put up the scaffolding and a view of the front of the building.

Photo 23rd March : Today the lads finished the blocks and Vinny puts the last one in and is delighted..also lads stand in for a photo...Declan and Vinny finish up today..thanks for all your hard work..


Photo 11th March: Window Sills going in and upstairs blocked except for gable ends....these will do done next week.

Photo 5th March : Nice view of the side of the new building.

Photo 19th Feb : Back wall finished now...everything going well....

Photo 15th Feb : Lads putting up the back wall and Vinny poses for the photo shoot..

Photo 9th Feb 2011 : A week on and a huge amount of work done in only 1 week..Hollowcore in..Declan and Mark laying block as quick as they are getting them..heating sorted out...electrics nearly sorted....more windows...alot of decisions made...good week all round..

Photo 2nd Feb 2011 : we're going up....Photos taken as Hollowcore going in!!

New Year!! - Photo 13th Jan 2011 : Lads making great progress and we got them all out for a photo...new development taking shape...

Photo 3rd Dec 2010 : Photos taken at 12:03 and the show was falling..this is the view from the new meeting room...a lovely view out onto the pitch.
 
Photo 1st Dec 2010 : It was late and the snow is down now for the last few days. Lads still made progress earlier in the week.
 
Photo 18th Nov 2010 : Wall are going up well!!

Photo 10th Nov 2010 - Lads blocking away again after the bad weather for the last 10 days.

Photo 22nd October - Steel Structure is Up and building is starting to take shape.

Photo 14th October - All the lads working hard onsite today.

Photo 13th October - First Day of Blocks - Photo Taken 18:56...it was getting dark.

Photo 12th October - Footpaths going in.

Photo 8th October - Getting Ready for footpaths.

Photo 6th October - Site busy but Ger wasn't!!

Photo 2nd October - Still working on foundations.
 
Photo 29th September 2010 - Concrete poured.

Photo 28th September 2010 - Raft foundation going in.

Photo 23rd September 2010 - Preparing site for foundations.

Photo 21st September 2010 - Start of Project and Site marked out!!